| SEQ001 |
Phase 1 - Living Room & Infrastructure |
Project Kickoff |
|
1 |
1 wk |
Verify zoning - set up project management - open bank account |
- |
Yes
|
| SEQ002 |
Phase 1 - Living Room & Infrastructure |
Engineering Quotes |
|
1-2 |
2 wk |
Get 3 structural engineer quotes - get 3 HVAC quotes |
- |
Yes
|
| SEQ040 |
Phase 2 - Kitchen & Finishes |
Home Automation Server Setup |
|
1-2 |
2 wk |
Install HAOS on TRIGKEY - configure Z-Wave - pair locks |
SEQ001 |
No
|
| SEQ045 |
Phase 1 - Living Room & Infrastructure |
E10 Pre-Order |
|
1 |
1 wk |
Place $10 pre-order deposit for Anker E10 |
- |
No
|
| SEQ003 |
Phase 1 - Living Room & Infrastructure |
Assessments |
|
2-4 |
3 wk |
Roof inspection - electrical inspection - plumbing scope |
- |
No
|
| SEQ004 |
Phase 1 - Living Room & Infrastructure |
Hire Engineering |
|
2-3 |
2 wk |
Select and engage structural engineer |
SEQ002 |
Yes
|
| SEQ005 |
Phase 1 - Living Room & Infrastructure |
Hire HVAC |
|
2-3 |
2 wk |
Select and engage HVAC contractor |
SEQ002 |
Yes
|
| SEQ006 |
Phase 2 - Kitchen & Finishes |
Kitchen Design |
|
2-5 |
4 wk |
Finalize kitchen layout with all appliances dimensioned |
SEQ004 staircase location |
Yes
|
| SEQ041 |
Phase 2 - Kitchen & Finishes |
Camera and Network Planning |
|
2-4 |
3 wk |
Plan camera locations - coordinate cable runs with electrician |
SEQ040, ACT005 kitchen layout |
No
|
| SEQ046 |
Phase 1 - Living Room & Infrastructure |
Energy System Design |
|
2-5 |
4 wk |
Get quotes - assess roof - design system |
- |
No
|
| SEQ007 |
Phase 1 - Living Room & Infrastructure |
Cabinet Sourcing |
|
3-6 |
4 wk |
Research vendors - get quotes - select cabinet maker |
SEQ006 |
Yes
|
| SEQ047 |
Phase 1 - Living Room & Infrastructure |
E10 Order Confirmation |
|
3 |
1 wk |
Confirm E10 order when Feb 4 sales open |
SEQ045 |
No
|
| SEQ008 |
Phase 1 - Living Room & Infrastructure |
Permit Drawings |
|
4-7 |
4 wk |
Architect/engineer complete permit drawings |
SEQ004, SEQ006 |
Yes
|
| SEQ009 |
Phase 1 - Living Room & Infrastructure |
Long-Lead Orders |
|
4-6 |
3 wk |
Order Impulse stove and other long-lead appliances |
SEQ006 |
Yes
|
| SEQ010 |
Phase 1 - Living Room & Infrastructure |
Permit Submission |
|
6-8 |
3 wk |
Submit to DC DOB via Permit Wizard |
SEQ008 |
Yes
|
| SEQ012 |
Phase 1 - Living Room & Infrastructure |
Cabinet Order |
|
7-8 |
2 wk |
Finalize cabinet order after design locked |
SEQ007 |
Yes
|
| SEQ011 |
Phase 1 - Living Room & Infrastructure |
Permit Review Wait |
|
8-16 |
8 wk |
DC DOB reviews - respond to any comments |
SEQ010 |
Yes
|
| SEQ048 |
Phase 1 - Living Room & Infrastructure |
E10 Installation |
|
8-10 |
2 wk |
Install E10 battery + Power Dock + Smart Generator |
SEQ047 |
No
|
| SEQ055 |
Phase 1 - Living Room & Infrastructure |
Furnishings Procurement |
|
8-28 |
20 wk |
Order and track delivery of rugs, couch, dining table, chairs, lamps, tables |
SEQ006 |
No
|
| SEQ013 |
Phase 2 - Kitchen & Finishes |
Demo Start |
|
16-17 |
2 wk |
Demo kitchen - guest bedroom closets - pantry for staircase |
SEQ011 permits |
Yes
|
| SEQ042 |
Phase 2 - Kitchen & Finishes |
Structured Cabling Install |
|
16-18 |
3 wk |
Run Cat6a to all camera locations during electrical rough-in |
SEQ041 walls open |
No
|
| SEQ014 |
Phase 2 - Kitchen & Finishes |
Structural Work |
|
17-19 |
3 wk |
Cut staircase opening - close window - install headers |
SEQ013 |
Yes
|
| SEQ015 |
Phase 1 - Living Room & Infrastructure |
HVAC Rough-In |
|
18-21 |
4 wk |
New ductwork throughout - equipment rough-in |
SEQ013, SEQ014 |
Yes
|
| SEQ016 |
Phase 1 - Living Room & Infrastructure |
Electrical Rough-In |
|
18-20 |
3 wk |
Panel upgrade - new circuits - boxes installed |
SEQ013 |
Yes
|
| SEQ017 |
Phase 1 - Living Room & Infrastructure |
Plumbing Rough-In |
|
18-20 |
3 wk |
New supply and drain for kitchen wet bar espresso |
SEQ013 |
Yes
|
| SEQ054 |
Phase 4 - Bathroom & Final |
Back Door Widening |
|
18-20 |
2 wk |
Structural header installation, door opening widening, high-end exterior door installation |
SEQ008, SEQ013 |
Yes
|
| SEQ056 |
Phase 4 - Bathroom & Final |
Heat Trace Installation |
|
18-19 |
1 wk |
Install self-regulating heat trace cable on main water entry and any supply lines in exterior walls or near foundation |
SEQ017, SEQ048 |
No
|
| SEQ057 |
Phase 1 - Living Room & Infrastructure |
Water Treatment Installation |
|
18-20 |
2 wk |
Install water softener, filters, UV system during plumbing rough-in |
SEQ017 plumbing rough-in |
No
|
| SEQ058 |
Phase 1 - Living Room & Infrastructure |
Humidity System Installation |
|
19-21 |
2 wk |
Install whole house humidifier and dehumidifier with ductwork integration |
SEQ015 HVAC rough-in, SEQ025 ductwork |
No
|
| SEQ061 |
Phase 1 - Living Room & Infrastructure |
Air Purification System Installation |
|
19-21 |
2 wk |
Install media air cleaner, PCO system, UV-C germicidal during HVAC installation |
SEQ015 HVAC rough-in, SEQ058 humidity systems |
No
|
| SEQ043 |
Phase 2 - Kitchen & Finishes |
Camera Network Setup |
|
20-21 |
2 wk |
Install PoE switch - mount cameras - configure Frigate |
SEQ042 drywall complete |
No
|
| SEQ049 |
Phase 1 - Living Room & Infrastructure |
Solar Installation |
|
20-24 |
4 wk |
Install 14-16 kW solar array |
SEQ048 |
No
|
| SEQ053 |
Phase 1 - Living Room & Infrastructure |
Window Replacements |
|
20-22 |
2 wk |
Replace 3 kitchen windows and 1 living room window with high-end energy efficient windows |
SEQ014 |
No
|
| SEQ018 |
Phase 1 - Living Room & Infrastructure |
Rough Inspections |
|
21-22 |
2 wk |
Electrical plumbing mechanical structural inspections |
SEQ014, SEQ015, SEQ016, SEQ017 |
Yes
|
| SEQ019 |
Phase 1 - Living Room & Infrastructure |
Insulation |
|
22-23 |
1 wk |
Insulate as needed |
SEQ018 |
No
|
| SEQ052 |
Phase 4 - Bathroom & Final |
Fireplace Conversions |
|
22-26 |
4 wk |
Gas line installation, direct-vent insert installation, custom surrounds for 5 fireplaces |
SEQ015, SEQ025 |
Yes
|
| SEQ020 |
Phase 1 - Living Room & Infrastructure |
Drywall |
|
23-25 |
3 wk |
Hang tape mud and finish drywall |
SEQ019 |
Yes
|
| SEQ021 |
Phase 2 - Kitchen & Finishes |
Staircase Finish |
|
24-26 |
3 wk |
Treads risers railings trim |
SEQ018 |
Yes
|
| SEQ050 |
Phase 1 - Living Room & Infrastructure |
System Integration |
|
24-26 |
2 wk |
Connect solar to E10 - configure monitoring |
SEQ048, SEQ049 |
No
|
| SEQ022 |
Phase 2 - Kitchen & Finishes |
Cabinet Installation |
|
26-28 |
3 wk |
Install all kitchen cabinets |
SEQ020 plus cabinets delivered |
Yes
|
| SEQ044 |
Phase 1 - Living Room & Infrastructure |
HVAC Integration |
|
26-27 |
2 wk |
Connect new HVAC to Home Assistant - configure automations |
W025 HVAC commissioned, SEQ040 |
No
|
| SEQ051 |
Phase 1 - Living Room & Infrastructure |
SREC Registration |
|
26-28 |
2 wk |
Register system - set up SREC sales |
SEQ050 |
No
|
| SEQ024 |
Phase 1 - Living Room & Infrastructure |
Wet Bar and Built-ins |
|
27-29 |
3 wk |
Install wet bar and living room built-ins |
SEQ020 |
No
|
| SEQ025 |
Phase 1 - Living Room & Infrastructure |
HVAC Finish |
|
27-28 |
2 wk |
Install equipment - connect ductwork - commission |
SEQ020 |
Yes
|
| SEQ059 |
Phase 1 - Living Room & Infrastructure |
Humidity Monitoring Setup |
|
27-28 |
1 wk |
Install humidity sensors on each floor, configure Home Assistant automations |
SEQ058 humidity systems, SEQ040 HA server |
No
|
| SEQ060 |
Phase 1 - Living Room & Infrastructure |
Water System Monitoring |
|
27-28 |
1 wk |
Install flow and pressure sensors, configure Home Assistant monitoring |
SEQ057 water treatment, SEQ040 HA server |
No
|
| SEQ062 |
Phase 1 - Living Room & Infrastructure |
IAQ Monitoring Setup |
|
27-28 |
1 wk |
Install IAQ monitors on each floor, configure Home Assistant dashboards and automations |
SEQ061 air purification, SEQ059 humidity monitoring |
No
|
| SEQ023 |
Phase 1 - Living Room & Infrastructure |
Countertop Template |
|
28 |
1 wk |
Template quartzite countertops |
SEQ022 |
Yes
|
| SEQ028 |
Phase 2 - Kitchen & Finishes |
Paint |
|
29-31 |
3 wk |
Prime and paint main floor |
SEQ020, SEQ022 |
No
|
| SEQ026 |
Phase 1 - Living Room & Infrastructure |
Countertop Install |
|
30 |
1 wk |
Install quartzite countertops |
SEQ023 plus fabrication |
Yes
|
| SEQ027 |
Phase 2 - Kitchen & Finishes |
Appliance Install |
|
30-31 |
2 wk |
Install all kitchen appliances |
SEQ022, SEQ026 |
Yes
|
| SEQ029 |
Phase 2 - Kitchen & Finishes |
Floor Refinishing |
|
32-33 |
2 wk |
Sand and refinish hardwood |
SEQ020, SEQ024, SEQ025, SEQ026, SEQ027, SEQ028 |
Yes
|
| SEQ030 |
Phase 1 - Living Room & Infrastructure |
Final Inspections |
|
33-34 |
2 wk |
Final building electrical plumbing mechanical |
SEQ025, SEQ026, SEQ027, SEQ028, SEQ029 |
Yes
|
| SEQ031 |
Phase 1 - Living Room & Infrastructure |
Move Back to Main |
|
34 |
1 wk |
Move back to main floor |
SEQ030 |
Yes
|
| SEQ032 |
Phase 3 - Basement & Lower Level |
Master Bath and Closet |
|
34-46 |
12 wk |
Gut master bath - reconfigure closet - full renovation |
SEQ031 |
No
|
| SEQ033 |
Phase 3 - Basement & Lower Level |
Bedroom Split |
|
36-42 |
6 wk |
Add wall to split bedroom |
SEQ031 |
No
|
| SEQ034 |
Phase 4 - Bathroom & Final |
Other Bathrooms |
|
42-52 |
10 wk |
Replace fixtures in 5 bathrooms |
SEQ031 |
No
|
| SEQ035 |
Phase 2 - Kitchen & Finishes |
Front Door |
|
TBD |
8-12 wk |
Replace and widen front door |
SEQ001 |
No
|
| SEQ036 |
Phase 2 - Kitchen & Finishes |
Metal Staircase |
|
TBD |
8-12 wk |
Rebuild front entry stairs |
SEQ001 |
No
|
| SEQ037 |
Phase 2 - Kitchen & Finishes |
Exterior Work |
|
TBD |
4-8 wk |
Repoint masonry and paint exterior |
SEQ001 |
No
|
| SEQ038 |
Future |
Roof |
|
TBD |
2-4 wk |
Replace roof |
SEQ003 |
No
|
| SEQ039 |
Future |
Basement |
|
TBD |
TBD wk |
Renovate basement |
SEQ031 |
No
|