ID Phase Milestone Status Weeks Duration Key Activities Dependencies Critical
SEQ001 Phase 1 - Living Room & Infrastructure Project Kickoff 1 1 wk Verify zoning - set up project management - open bank account - Yes
SEQ002 Phase 1 - Living Room & Infrastructure Engineering Quotes 1-2 2 wk Get 3 structural engineer quotes - get 3 HVAC quotes - Yes
SEQ040 Phase 2 - Kitchen & Finishes Home Automation Server Setup 1-2 2 wk Install HAOS on TRIGKEY - configure Z-Wave - pair locks SEQ001 No
SEQ045 Phase 1 - Living Room & Infrastructure E10 Pre-Order 1 1 wk Place $10 pre-order deposit for Anker E10 - No
SEQ003 Phase 1 - Living Room & Infrastructure Assessments 2-4 3 wk Roof inspection - electrical inspection - plumbing scope - No
SEQ004 Phase 1 - Living Room & Infrastructure Hire Engineering 2-3 2 wk Select and engage structural engineer SEQ002 Yes
SEQ005 Phase 1 - Living Room & Infrastructure Hire HVAC 2-3 2 wk Select and engage HVAC contractor SEQ002 Yes
SEQ006 Phase 2 - Kitchen & Finishes Kitchen Design 2-5 4 wk Finalize kitchen layout with all appliances dimensioned SEQ004 staircase location Yes
SEQ041 Phase 2 - Kitchen & Finishes Camera and Network Planning 2-4 3 wk Plan camera locations - coordinate cable runs with electrician SEQ040, ACT005 kitchen layout No
SEQ046 Phase 1 - Living Room & Infrastructure Energy System Design 2-5 4 wk Get quotes - assess roof - design system - No
SEQ007 Phase 1 - Living Room & Infrastructure Cabinet Sourcing 3-6 4 wk Research vendors - get quotes - select cabinet maker SEQ006 Yes
SEQ047 Phase 1 - Living Room & Infrastructure E10 Order Confirmation 3 1 wk Confirm E10 order when Feb 4 sales open SEQ045 No
SEQ008 Phase 1 - Living Room & Infrastructure Permit Drawings 4-7 4 wk Architect/engineer complete permit drawings SEQ004, SEQ006 Yes
SEQ009 Phase 1 - Living Room & Infrastructure Long-Lead Orders 4-6 3 wk Order Impulse stove and other long-lead appliances SEQ006 Yes
SEQ010 Phase 1 - Living Room & Infrastructure Permit Submission 6-8 3 wk Submit to DC DOB via Permit Wizard SEQ008 Yes
SEQ012 Phase 1 - Living Room & Infrastructure Cabinet Order 7-8 2 wk Finalize cabinet order after design locked SEQ007 Yes
SEQ011 Phase 1 - Living Room & Infrastructure Permit Review Wait 8-16 8 wk DC DOB reviews - respond to any comments SEQ010 Yes
SEQ048 Phase 1 - Living Room & Infrastructure E10 Installation 8-10 2 wk Install E10 battery + Power Dock + Smart Generator SEQ047 No
SEQ055 Phase 1 - Living Room & Infrastructure Furnishings Procurement 8-28 20 wk Order and track delivery of rugs, couch, dining table, chairs, lamps, tables SEQ006 No
SEQ013 Phase 2 - Kitchen & Finishes Demo Start 16-17 2 wk Demo kitchen - guest bedroom closets - pantry for staircase SEQ011 permits Yes
SEQ042 Phase 2 - Kitchen & Finishes Structured Cabling Install 16-18 3 wk Run Cat6a to all camera locations during electrical rough-in SEQ041 walls open No
SEQ014 Phase 2 - Kitchen & Finishes Structural Work 17-19 3 wk Cut staircase opening - close window - install headers SEQ013 Yes
SEQ015 Phase 1 - Living Room & Infrastructure HVAC Rough-In 18-21 4 wk New ductwork throughout - equipment rough-in SEQ013, SEQ014 Yes
SEQ016 Phase 1 - Living Room & Infrastructure Electrical Rough-In 18-20 3 wk Panel upgrade - new circuits - boxes installed SEQ013 Yes
SEQ017 Phase 1 - Living Room & Infrastructure Plumbing Rough-In 18-20 3 wk New supply and drain for kitchen wet bar espresso SEQ013 Yes
SEQ054 Phase 4 - Bathroom & Final Back Door Widening 18-20 2 wk Structural header installation, door opening widening, high-end exterior door installation SEQ008, SEQ013 Yes
SEQ056 Phase 4 - Bathroom & Final Heat Trace Installation 18-19 1 wk Install self-regulating heat trace cable on main water entry and any supply lines in exterior walls or near foundation SEQ017, SEQ048 No
SEQ057 Phase 1 - Living Room & Infrastructure Water Treatment Installation 18-20 2 wk Install water softener, filters, UV system during plumbing rough-in SEQ017 plumbing rough-in No
SEQ058 Phase 1 - Living Room & Infrastructure Humidity System Installation 19-21 2 wk Install whole house humidifier and dehumidifier with ductwork integration SEQ015 HVAC rough-in, SEQ025 ductwork No
SEQ061 Phase 1 - Living Room & Infrastructure Air Purification System Installation 19-21 2 wk Install media air cleaner, PCO system, UV-C germicidal during HVAC installation SEQ015 HVAC rough-in, SEQ058 humidity systems No
SEQ043 Phase 2 - Kitchen & Finishes Camera Network Setup 20-21 2 wk Install PoE switch - mount cameras - configure Frigate SEQ042 drywall complete No
SEQ049 Phase 1 - Living Room & Infrastructure Solar Installation 20-24 4 wk Install 14-16 kW solar array SEQ048 No
SEQ053 Phase 1 - Living Room & Infrastructure Window Replacements 20-22 2 wk Replace 3 kitchen windows and 1 living room window with high-end energy efficient windows SEQ014 No
SEQ018 Phase 1 - Living Room & Infrastructure Rough Inspections 21-22 2 wk Electrical plumbing mechanical structural inspections SEQ014, SEQ015, SEQ016, SEQ017 Yes
SEQ019 Phase 1 - Living Room & Infrastructure Insulation 22-23 1 wk Insulate as needed SEQ018 No
SEQ052 Phase 4 - Bathroom & Final Fireplace Conversions 22-26 4 wk Gas line installation, direct-vent insert installation, custom surrounds for 5 fireplaces SEQ015, SEQ025 Yes
SEQ020 Phase 1 - Living Room & Infrastructure Drywall 23-25 3 wk Hang tape mud and finish drywall SEQ019 Yes
SEQ021 Phase 2 - Kitchen & Finishes Staircase Finish 24-26 3 wk Treads risers railings trim SEQ018 Yes
SEQ050 Phase 1 - Living Room & Infrastructure System Integration 24-26 2 wk Connect solar to E10 - configure monitoring SEQ048, SEQ049 No
SEQ022 Phase 2 - Kitchen & Finishes Cabinet Installation 26-28 3 wk Install all kitchen cabinets SEQ020 plus cabinets delivered Yes
SEQ044 Phase 1 - Living Room & Infrastructure HVAC Integration 26-27 2 wk Connect new HVAC to Home Assistant - configure automations W025 HVAC commissioned, SEQ040 No
SEQ051 Phase 1 - Living Room & Infrastructure SREC Registration 26-28 2 wk Register system - set up SREC sales SEQ050 No
SEQ024 Phase 1 - Living Room & Infrastructure Wet Bar and Built-ins 27-29 3 wk Install wet bar and living room built-ins SEQ020 No
SEQ025 Phase 1 - Living Room & Infrastructure HVAC Finish 27-28 2 wk Install equipment - connect ductwork - commission SEQ020 Yes
SEQ059 Phase 1 - Living Room & Infrastructure Humidity Monitoring Setup 27-28 1 wk Install humidity sensors on each floor, configure Home Assistant automations SEQ058 humidity systems, SEQ040 HA server No
SEQ060 Phase 1 - Living Room & Infrastructure Water System Monitoring 27-28 1 wk Install flow and pressure sensors, configure Home Assistant monitoring SEQ057 water treatment, SEQ040 HA server No
SEQ062 Phase 1 - Living Room & Infrastructure IAQ Monitoring Setup 27-28 1 wk Install IAQ monitors on each floor, configure Home Assistant dashboards and automations SEQ061 air purification, SEQ059 humidity monitoring No
SEQ023 Phase 1 - Living Room & Infrastructure Countertop Template 28 1 wk Template quartzite countertops SEQ022 Yes
SEQ028 Phase 2 - Kitchen & Finishes Paint 29-31 3 wk Prime and paint main floor SEQ020, SEQ022 No
SEQ026 Phase 1 - Living Room & Infrastructure Countertop Install 30 1 wk Install quartzite countertops SEQ023 plus fabrication Yes
SEQ027 Phase 2 - Kitchen & Finishes Appliance Install 30-31 2 wk Install all kitchen appliances SEQ022, SEQ026 Yes
SEQ029 Phase 2 - Kitchen & Finishes Floor Refinishing 32-33 2 wk Sand and refinish hardwood SEQ020, SEQ024, SEQ025, SEQ026, SEQ027, SEQ028 Yes
SEQ030 Phase 1 - Living Room & Infrastructure Final Inspections 33-34 2 wk Final building electrical plumbing mechanical SEQ025, SEQ026, SEQ027, SEQ028, SEQ029 Yes
SEQ031 Phase 1 - Living Room & Infrastructure Move Back to Main 34 1 wk Move back to main floor SEQ030 Yes
SEQ032 Phase 3 - Basement & Lower Level Master Bath and Closet 34-46 12 wk Gut master bath - reconfigure closet - full renovation SEQ031 No
SEQ033 Phase 3 - Basement & Lower Level Bedroom Split 36-42 6 wk Add wall to split bedroom SEQ031 No
SEQ034 Phase 4 - Bathroom & Final Other Bathrooms 42-52 10 wk Replace fixtures in 5 bathrooms SEQ031 No
SEQ035 Phase 2 - Kitchen & Finishes Front Door TBD 8-12 wk Replace and widen front door SEQ001 No
SEQ036 Phase 2 - Kitchen & Finishes Metal Staircase TBD 8-12 wk Rebuild front entry stairs SEQ001 No
SEQ037 Phase 2 - Kitchen & Finishes Exterior Work TBD 4-8 wk Repoint masonry and paint exterior SEQ001 No
SEQ038 Future Roof TBD 2-4 wk Replace roof SEQ003 No
SEQ039 Future Basement TBD TBD wk Renovate basement SEQ031 No