$730,027
Total Low Estimate
$1,243,098
Total High Estimate
$986,562
Midpoint
Budget by Category (click to expand)
Category Items Low Estimate High Estimate % of Total
Kitchen 19 $156,800 $256,900
21%
Subcategory Phase Priority Low High Notes
Cabinets Phase 2 - Kitchen & Finishes High $45,000 $90,000 Baltic birch with Kessebohmer pull-downs - longest...
Countertops Phase 2 - Kitchen & Finishes High $12,000 $25,000 Quartzite - template after cabinets
Island Phase 2 - Kitchen & Finishes High $8,000 $18,000 Custom island - coordinate with cabinet vendor
Structural - Window Closure Phase 2 - Kitchen & Finishes High $8,000 $15,000 Side window - requires structural engineer
Appliances - Refrigerator Phase 2 - Kitchen & Finishes High $9,000 $15,000 Built-in panel ready
Appliances - Wall Ovens Phase 2 - Kitchen & Finishes High $11,500 $14,000 Full size + combo microwave stack
Dining Chairs Phase 2 - Kitchen & Finishes Med $10,000 $10,000 Set of high-end dining chairs
Appliances - Espresso Machine Phase 2 - Kitchen & Finishes High $8,500 $9,000 Miele CVA 7775 with DirectWater - per Appliance Op...
Rough Electrical Phase 2 - Kitchen & Finishes High $5,000 $9,000 Panel upgrade and dedicated circuits
Window Replacement (3) Phase 2 - Kitchen & Finishes High $4,500 $7,500 3 high-end energy efficient windows at $1,500-$2,5...
Rough Plumbing Phase 2 - Kitchen & Finishes High $4,000 $7,000 New plumbing for dual dishwashers sink espresso
Rug Phase 2 - Kitchen & Finishes Med $6,000 $6,000 High-end area rug for dining area
Appliances - Cooktop Phase 2 - Kitchen & Finishes High $5,900 $5,900 Impulse Labs induction
Appliances - Vacuum Sealer Phase 2 - Kitchen & Finishes High $3,600 $5,000 Miele EVS 7010
Demolition Phase 2 - Kitchen & Finishes High $3,000 $5,000 Demo existing kitchen
Dining Table Phase 2 - Kitchen & Finishes Med $5,000 $5,000 High-end dining table
Appliances - Installation Labor Phase 2 - Kitchen & Finishes High $2,000 $4,000 Coordinate all appliance connections
Drapes Phase 2 - Kitchen & Finishes Med $4,000 $4,000 Custom window treatments
Appliances - Second Dishwasher Phase 2 - Kitchen & Finishes High $1,800 $2,500 Miele 7000 series to match
HVAC 5 $63,000 $115,000
9%
Subcategory Phase Priority Low High Notes
System 1 - Main Floor Phase 1 - Living Room & Infrastructure High $15,000 $27,000 Cold-climate heat pump - replaces gas furnace + AC
System 2 - Upper Floor Phase 1 - Living Room & Infrastructure High $15,000 $27,000 Cold-climate heat pump - replaces gas furnace + AC
System 3 - Basement Phase 1 - Living Room & Infrastructure High $15,000 $26,000 Cold-climate heat pump - replaces gas furnace + AC
Ductwork Redesign - Noise Phase 1 - Living Room & Infrastructure High $10,000 $20,000 Properly sized trunk lines, dampers, insulated fle...
Mechanical Room Buildout Phase 1 - Living Room & Infrastructure High $8,000 $15,000 Equipment room with sound isolation and proper ven...
Living Room 10 $74,000 $114,500
9%
Subcategory Phase Priority Low High Notes
Wet Bar + Built-ins Combined Phase 1 - Living Room & Infrastructure Med $30,000 $40,000 Combined custom millwork - wet bar with integrated...
Couch Phase 1 - Living Room & Infrastructure Med $20,000 $35,000 High-end custom sofa
Back Entrance Door - Replace Phase 1 - Living Room & Infrastructure High $5,000 $12,000 high-end exterior door + structural header
Rug Phase 1 - Living Room & Infrastructure Med $6,000 $10,000 High-end area rug
Demo and Conversion Phase 1 - Living Room & Infrastructure Med $3,000 $6,000 Remove closets open space
Drapes Phase 1 - Living Room & Infrastructure Med $3,000 $3,000 Custom window treatments
Window Replacement Phase 1 - Living Room & Infrastructure Med $1,500 $3,000 High-end energy efficient window
Lamps Phase 1 - Living Room & Infrastructure Low $3,000 $3,000 Designer lighting
Table Phase 1 - Living Room & Infrastructure Low $1,500 $1,500 Accent/side table
Hardware on Built-ins Phase 1 - Living Room & Infrastructure Low $1,000 $1,000 High-end cabinet hardware for built-ins
Soft Costs 4 $61,000 $113,000
9%
Subcategory Phase Priority Low High Notes
Contingency 15% Phase 1 - Living Room & Infrastructure High $52,500 $90,000 15% of Phase 1 scope - increased for 1905 home unk...
Permits Phase 1 - Living Room & Infrastructure High $4,000 $8,000 Building plus supplemental permits
Architect/Designer Phase 1 - Living Room & Infrastructure High $2,000 $8,000 Permit drawings kitchen design
Structural Engineer Phase 1 - Living Room & Infrastructure High $2,500 $7,000 Drawings for staircase window door + electrical lo...
Exterior 4 $47,000 $105,000
8%
Subcategory Phase Priority Low High Notes
Metal Staircase Rebuild Phase 4 - Bathroom & Final Low $20,000 $45,000 May need DDOT permit
Front Door Phase 2 - Kitchen & Finishes Low $12,000 $25,000 Antique door structural header
Masonry Repointing Phase 4 - Bathroom & Final Low $8,000 $18,000 Assess extent during paint prep
Exterior Paint Phase 4 - Bathroom & Final Low $7,000 $17,000 High-end exterior
Master Bathroom 1 $50,000 $90,000
7%
Subcategory Phase Priority Low High Notes
Gut Renovation Phase 3 - Basement & Lower Level High $50,000 $90,000 High-end fixtures custom tile
Energy System 9 $70,899 $89,099
7%
Subcategory Phase Priority Low High Notes
Solar Array (14-16kW) Phase 1 - Living Room & Infrastructure High $42,000 $50,000 Panels inverters racking monitoring
Solar Installation Labor Phase 1 - Living Room & Infrastructure High $6,000 $10,000 Professional install + permitting
E10 Base Bundle Phase 1 - Living Room & Infrastructure High $7,399 $7,399 E10 + Power Dock + Smart Generator - $500 pre-orde...
ANNUAL SREC INCOME (benefit) Phase 1 - Living Room & Infrastructure High $5,600 $7,200 INCOME - 14-18 SRECs at ~$400 each
E10 Additional Batteries (2x6kWh) Phase 1 - Living Room & Infrastructure High $4,000 $5,000 Expand to 18kWh total
E10 Installation Phase 1 - Living Room & Infrastructure High $2,000 $3,500 Professional installation
ANNUAL ELECTRIC SAVINGS (benefit) Phase 1 - Living Room & Infrastructure High $2,500 $3,500 SAVINGS - Offset 20000+ kWh
ANNUAL GAS SAVINGS (benefit) Phase 1 - Living Room & Infrastructure High $1,400 $2,000 SAVINGS - Heat pump replaces gas furnace
Pepco Interconnection Phase 1 - Living Room & Infrastructure Med $0 $500 Utility interconnection
Fireplaces 5 $40,000 $75,000
6%
Subcategory Phase Priority Low High Notes
Living Room Fireplace Phase 1 - Living Room & Infrastructure High $8,000 $15,000 High-end gas vented direct-vent insert with custom...
Family Room Fireplace Phase 4 - Bathroom & Final High $8,000 $15,000 High-end gas vented direct-vent insert with custom...
Master Bedroom Fireplace Phase 3 - Basement & Lower Level High $8,000 $15,000 High-end gas vented direct-vent insert with custom...
Dining Room Fireplace Phase 4 - Bathroom & Final High $8,000 $15,000 High-end gas vented direct-vent insert with custom...
Basement Fireplace Phase 4 - Bathroom & Final High $8,000 $15,000 High-end gas vented direct-vent insert with custom...
Structural 2 $25,000 $47,000
4%
Subcategory Phase Priority Low High Notes
Interior Staircase - Rough Phase 2 - Kitchen & Finishes High $20,000 $35,000 Cut opening - structural work
Interior Staircase - Finish Phase 2 - Kitchen & Finishes High $5,000 $12,000 Treads risers railings
Future 2 $25,000 $45,000
4%
Subcategory Phase Priority Low High Notes
Roof Replacement Future Med $25,000 $45,000 Patched currently - timeline TBD
Basement Renovation Future Low $0 $0 Scope TBD
Bathrooms 5 $40,000 $40,000
3%
Subcategory Phase Priority Low High Notes
Bathroom 2 Fixtures Phase 4 - Bathroom & Final Med $8,000 $8,000 Guest bathroom - updated to $8k per user request
Bathroom 3 Fixtures Phase 4 - Bathroom & Final Med $8,000 $8,000 Guest bathroom - updated to $8k per user request
Bathroom 4 Fixtures Phase 4 - Bathroom & Final Med $8,000 $8,000 Guest bathroom - updated to $8k per user request
Bathroom 5 Fixtures Phase 4 - Bathroom & Final Med $8,000 $8,000 Guest bathroom - updated to $8k per user request
Bathroom 6 Fixtures Phase 4 - Bathroom & Final Med $8,000 $8,000 Guest bathroom - updated to $8k per user request
Paint 1 $18,000 $30,000
2%
Subcategory Phase Priority Low High Notes
Interior Whole House Phase 2 - Kitchen & Finishes Med $18,000 $30,000 Farrow & Ball quality
Bedroom 1 $12,000 $25,000
2%
Subcategory Phase Priority Low High Notes
Split into Two Phase 3 - Basement & Lower Level Med $12,000 $25,000 Add wall - possibly structural
Electrical 2 $10,500 $24,500
2%
Subcategory Phase Priority Low High Notes
Inspection and Rewiring Phase 1 - Living Room & Infrastructure Med $8,000 $20,000 Selective rewiring as needed
Panel Upgrade Phase 1 - Living Room & Infrastructure High $2,500 $4,500 200A minimum
Plumbing 2 $6,000 $17,100
1%
Subcategory Phase Priority Low High Notes
Inspection and Updates Phase 1 - Living Room & Infrastructure Med $5,000 $15,000 Selective updates as needed
Heat Trace Cable - Freeze Protection Phase 1 - Living Room & Infrastructure High $1,000 $2,100 Self-regulating heat trace on vulnerable supply li...
Master Closet 1 $8,000 $15,000
1%
Subcategory Phase Priority Low High Notes
Reconfiguration Phase 3 - Basement & Lower Level High $8,000 $15,000 Expand into bedroom space
Water Treatment 5 $7,200 $11,900
1%
Subcategory Phase Priority Low High Notes
Water Softener System Phase 1 - Living Room & Infrastructure High $3,500 $5,500 Fleck/Clack valve - DC hard water 120-150 ppm
Installation Labor Phase 1 - Living Room & Infrastructure High $1,500 $2,500 Licensed plumber - bypass valves, gauges, PRV
Sediment + Carbon Filtration Phase 1 - Living Room & Infrastructure High $1,200 $2,000 Multi-stage whole house filtration
UV Treatment System Phase 1 - Living Room & Infrastructure High $800 $1,500 Viqua/Sterilight 99.99% pathogen elimination
Monitoring Sensors Phase 1 - Living Room & Infrastructure Med $200 $400 Flow and pressure sensors - Home Assistant
Humidity Control 5 $5,550 $9,500
1%
Subcategory Phase Priority Low High Notes
Whole House Dehumidifier (Ducted) Phase 1 - Living Room & Infrastructure High $2,000 $3,500 Aprilaire E130 or Santa Fe - DC summer humidity
Whole House Humidifier (Steam) Phase 1 - Living Room & Infrastructure High $1,800 $3,000 Aprilaire 800 or Honeywell HM750A - 3 floors
Installation Labor Phase 1 - Living Room & Infrastructure High $1,500 $2,500 HVAC contractor - duct integration + condensate
Monitoring Sensors (3-floor) Phase 1 - Living Room & Infrastructure High $150 $300 Zigbee temp/humidity sensors per floor
Automation Integration Phase 1 - Living Room & Infrastructure Med $100 $200 Home Assistant automations by season
Air Purification 6 $4,000 $7,400
1%
Subcategory Phase Priority Low High Notes
PCO System (Formaldehyde/VOC Destruction) Phase 1 - Living Room & Infrastructure High $1,200 $2,000 REME HALO-LED or Air Oasis - continuous oxidation ...
MERV 16 Media Air Cleaner Phase 1 - Living Room & Infrastructure High $800 $1,500 Hospital-grade 5-inch media filter - 0.3 micron ca...
Installation Labor Phase 1 - Living Room & Infrastructure High $800 $1,500 HVAC integration with ductwork
UV-C Germicidal System Phase 1 - Living Room & Infrastructure High $600 $1,200 Coil and airstream disinfection
Activated Carbon VOC Filter Phase 1 - Living Room & Infrastructure Med $300 $600 Cooking odors and chemical off-gassing
IAQ Monitoring System Phase 1 - Living Room & Infrastructure High $300 $600 Awair Element - PM2.5 CO2 VOC monitoring
Flooring 1 $4,000 $7,000
1%
Subcategory Phase Priority Low High Notes
Hardwood Refinishing Phase 2 - Kitchen & Finishes High $4,000 $7,000 Main floor only
Home Automation 11 $2,078 $5,199
0%
Subcategory Phase Priority Low High Notes
IP Cameras - 4x 4K Phase 2 - Kitchen & Finishes Med $800 $2,400 Dahua/Hikvision/Amcrest/Reolink - RTSP required fo...
Cat6a Cabling - Labor and Materials Phase 2 - Kitchen & Finishes High $400 $800 Run during rough-in - 4+ camera runs plus network ...
NAS Storage - Phase 2 Phase 2 - Kitchen & Finishes Low $400 $800 Only when camera storage exceeds internal SSD
Smart Sensors - Phase 2 Phase 2 - Kitchen & Finishes Low $200 $600 Door/window/motion sensors - defer to Phase 2
Server - TRIGKEY N100 Mini PC Phase 2 - Kitchen & Finishes High $160 $160 Intel N100 16GB RAM 500GB SSD - runs Home Assistan...
PoE Switch - 8 Port Phase 2 - Kitchen & Finishes Med $60 $150 Powers cameras via single cable - enables VLAN iso...
Z-Wave Thermostat (if needed) Phase 2 - Kitchen & Finishes Med $0 $150 Only if new HVAC lacks native integration
UPS - Server Protection Phase 2 - Kitchen & Finishes High $50 $80 APC BE425M or similar - critical for lock reliabil...
ZBT-2 Zigbee/Thread Adapter Phase 2 - Kitchen & Finishes Low $0 $49 Only if HVAC or sensors require - assess after HVA...
USB Extension Cable Phase 2 - Kitchen & Finishes High $8 $10 6ft USB 2.0 - keeps adapter away from USB 3.0 inte...
Z-Wave Adapter - ZWA-2 Phase 2 - Kitchen & Finishes High $0 $0 Already owned
Total 101 $730,027 $1,243,098 100%