Verify zoning at maps.dcoz.dc.gov
Immediate
Confirmed RF-1 per user
→ Screenshot of zoning confirmation
Planning Homeowner
Complete
Pre-order Anker SOLIX E10 ($10 deposit)
Immediate
Refundable deposit - locks in pre-order pricing
→ $500 coupon + free 400W panel + 8yr warranty
Energy Homeowner
Not Started
Get 3 structural engineer quotes
Week 1-2
Need drawings for staircase + window closure
→ 3 written quotes with scope and timeline
Engineering Homeowner
Not Started
Get 3 HVAC contractor quotes
Week 1-2
Specify need for ductwork redesign and noise mitigation + whole house humidifier/dehumidifier
→ 3 written quotes with Manual J calculation
HVAC Homeowner
Not Started
Get roof inspection
Week 1-2
Know timeline for replacement - affects budget planning
→ Written inspection report
Planning Homeowner
Not Started
Set up project management system
Week 1-2
Notion Airtable or even Google Sheets - track everything
→ Chosen system configured
Planning Homeowner
Not Started
Create master budget spreadsheet
Week 1-2
Track estimates vs actuals by category
→ Working budget tracker
Planning Homeowner or Claude
Not Started
Open dedicated renovation bank account
Week 1-2
Separate finances for clear tracking
→ Account opened
Financial Homeowner
Not Started
Install Home Assistant OS on TRIGKEY N100 mini PC
Week 1-2
Flash HAOS to USB - boot and install to internal SSD
→ Working Home Assistant installation
Home Automation Homeowner
Not Started
Configure ZWA-2 Z-Wave adapter with USB extension
Week 1-2
Use 6ft USB 2.0 extension to avoid USB 3.0 interference
→ Z-Wave JS integration configured
Home Automation Homeowner
Not Started
Pair Yale Assure 2 locks with Home Assistant
Week 1-2
Set up PIN codes and automations through Z-Wave JS
→ All locks paired and controllable
Home Automation Homeowner
Not Started
Set up UPS for home automation server
Week 1-2
APC BE425M or similar - critical for lock reliability during outages
→ UPS protecting server and network
Home Automation Homeowner
Not Started
Research DC water quality report for Capitol Hill 20002
Week 1-2
Check DC Water annual report - verify hardness and contaminants
→ DC Water quality data for 20002
Planning Homeowner or Claude
Not Started
Hire architect or designer for permit drawings
Week 3-4
Not Started
→ May be same firm as structural engineer
Hiring ACT014 structural engineer engaged
Not Started
Move cabinet vendor selection earlier (Week 4)
Week 3-4
8-16 week lead time requires ordering by Week 6 max - need buffer
→ Cabinet vendor selected and contract signed
Sourcing Homeowner
Not Started
Get quotes from fireplace contractors (5 gas vented conversions)
Week 3-4
High-end gas vented direct-vent inserts with custom surrounds - $8k-$15k each
→ Minimum 3 quotes for 5 fireplace conversions
Sourcing Homeowner
Not Started
Get structural assessment for back door widening
Week 3-4
Back entrance door widen requires structural header - coordinate with permit
→ Structural drawings for door widening with header requirements
Engineering Structural Engineer
Not Started
Finalize kitchen layout concept
Week 2-4
Drives cabinet design and permit drawings
→ Kitchen floor plan with appliance locations
Design Homeowner + Designer
Not Started
Research local DC Baltic birch cabinet makers
Week 2-4
Need shops that can integrate Kessebohmer hardware
→ List of 3-5 qualified shops with portfolios
Sourcing Homeowner or Claude
Not Started
Get cabinet quotes
Week 4-6
Include pull-down mechanisms in scope
→ 3 written quotes with timeline and specs
Sourcing Homeowner
Not Started
Order Impulse Labs stove
Week 4-6
8-12 week lead time - order early
→ Order confirmation
Procurement Homeowner
Not Started
Hire structural engineer
Week 2-3
Not Started
→ Select from quotes
Hiring ACT002 quotes received
Not Started
Hire HVAC contractor
Week 2-3
Not Started
→ Select from quotes - ensure Manual J included
Hiring ACT003 quotes received
Not Started
Submit permit application
Week 6-8
Not Started
→ Use DC Permit Wizard for residential - expect 30-45 day review
Permitting ACT014 ACT016 drawings complete
Not Started
Select cabinet vendor
Week 6-8
Not Started
→ Longest lead time item - critical path
Decision ACT007 quotes received
Not Started
Create appliance specification sheet
Week 2-3
Not Started
→ Needed for kitchen design and electrical planning
Planning
Not Started
Plan security camera locations - coordinate with electrical
Week 2-4
Run Cat6a during rough-in phase - cheaper than retrofitting
→ Camera location plan with cable runs
Home Automation Homeowner
Not Started
Research HVAC integration options for Home Assistant
Week 2-3
Check if new HVAC has native WiFi - may need Z-Wave thermostat
→ Integration plan documented
Home Automation Homeowner or Claude
Not Started
Run Cat6a cable to all camera locations during rough-in
Week 16-18
Future-proofs for 10GbE - much cheaper during renovation
→ Cat6a home runs to server location
Home Automation Electrician
Not Started
Get 3 solar installer quotes (DC area)
Week 2-4
Need installers experienced with battery integration
→ 3 written quotes with system designs
Energy Homeowner
Not Started
Verify roof solar potential
Week 2-3
South/East/West exposure - check for obstructions
→ Shading analysis and roof assessment
Energy Homeowner
Not Started
Get cold-climate heat pump quotes
Week 2-4
Specify cold-climate rated - Mitsubishi/Carrier/Bosch
→ 3 written quotes with Manual J
Energy Homeowner
Not Started
Confirm E10 order (Feb 4 launch)
Week 3
Use $500 coupon from pre-order
→ E10 + Power Dock + Smart Generator ordered
Energy Homeowner
Not Started
Coordinate HVAC with solar installer
Week 4-6
Solar sizing depends on heat pump load
→ Integrated system design
Energy Homeowner
Not Started
Schedule E10 installation
Week 6-8
Anker offers nationwide installation
→ Installation date confirmed
Energy Homeowner
Not Started
Get electrical engineer load calculation
Week 2-4
CRITICAL: 60A stove + 3 heat pumps + ovens + E10 battery requires verification
→ Load calculation report confirming 200A panel sufficiency
Engineering Homeowner
Not Started
Build 2-week permit buffer into schedule
Week 1
DC DOB often requires resubmissions - plan demo for Week 16 not Week 14
→ Updated project schedule with buffer
Planning Homeowner
Not Started
Research DC Baltic birch cabinet makers - specific vendors
Week 2-3
Replace TBD in Cabinet Options C003 with actual vendor names
→ List of 3-5 specific DC-area cabinet shops with contact info
Sourcing Homeowner or Claude
Not Started
Get quotes for window replacements (4 windows total)
Week 4-5
High-end energy efficient windows. Kitchen $4.5k-$7.5k, Living Room $1.5k-$3k
→ Window quotes for 3 kitchen + 1 living room windows
Sourcing Homeowner
Not Started
Get heat trace cable quote from plumber during rough-in scope
Week 4-6
Ask plumber to identify vulnerable pipe runs and quote heat trace installation. Much cheaper during rough-in than retrofit.
→ Quote for heat trace installation during rough-in
Plumbing Homeowner
Not Started
Get 3 quotes for whole home water treatment system
Week 2-4
Include softener + filters + UV - DC 20002 has 120-150 ppm hardness
→ 3 written quotes with equipment specs
Plumbing Homeowner
Not Started
Select water treatment vendor
Week 4-5
Select from quotes - ensure bypass valve included
→ Signed contract
Sourcing Homeowner
Not Started
Coordinate water treatment with plumber
Week 6-8
Install during plumbing rough-in for efficiency
→ Installation scheduled
Coordination Homeowner
Not Started
Get humidity control quotes from HVAC contractors
Week 2-4
Add humidifier + dehumidifier to HVAC contractor scope
→ Humidity equipment included in HVAC scope
HVAC Homeowner
Not Started
Research whole-house air purification options
Week 2-3
PCO vs ionization vs filtration - formaldehyde destruction capability
→ Air purification system recommendations
HVAC Homeowner or Claude
Not Started
Include air purification in HVAC contractor scope
Week 2-4
Request REME HALO + MERV 16 + UV-C in scope
→ Air purification included in HVAC quotes
HVAC Homeowner
Not Started
Get heat trace cable quote from plumber during rough-in scope
Week 4-6
Ask plumber to identify vulnerable pipe runs and quote heat trace installation. Much cheaper during rough-in than retrofit.
→ Quote for heat trace installation during rough-in
Plumbing Homeowner
Not Started
Order built-in espresso machine
Week 6-8
Miele CVA 7775 recommended - coordinate with cabinet dimensions
→ Order confirmation
Procurement Homeowner
Not Started
Order built-in vacuum sealer
Week 6-8
Miele EVS 7010 recommended
→ Order confirmation
Procurement Homeowner
Not Started
Order wall ovens
Week 6-8
Full size + combo microwave stack
→ Order confirmation
Procurement Homeowner
Not Started
Order built-in refrigerator
Week 6-8
Panel-ready - coordinate panel with cabinet vendor
→ Order confirmation
Procurement Homeowner
Not Started
Order second dishwasher
Week 6-8
Match existing Miele 7000 series
→ Order confirmation
Procurement Homeowner
Not Started
Schedule DCRA Homeowner Center consultation
Week 4-5
Not Started
→ Free consultation to review permit strategy
Permitting ACT005 scope defined
Not Started
Get electrical inspection of existing wiring
Week 4-6
Not Started
→ Determine extent of rewiring needed
Assessment
Not Started
Get plumbing scope of drain lines
Week 4-6
Not Started
→ Determine condition of existing drains
Assessment
Not Started
Finalize quartzite slab selection
Week 8-10
Not Started
→ Visit stone yards - select specific slabs
Design ACT021 cabinet design locked
Not Started
Interview general contractors OR confirm self-GC approach
Week 2-4
Not Started
→ Even self-GC may benefit from consulting with experienced GC
Planning
Not Started
Review insurance coverage
Week 2-4
May need builders risk policy during construction
→ Confirmation of adequate coverage
Financial Homeowner
Not Started
Plan temporary kitchen setup in basement
Week 6-8
Since youll live in basement during Phase 1
→ Basement kitchen functional
Logistics Homeowner
Not Started
Select and purchase IP cameras for Frigate NVR
Week 4-6
Dahua/Hikvision/Amcrest/Reolink with RTSP support required
→ 4 IP cameras ordered
Home Automation Homeowner
Not Started
Purchase PoE switch for camera network isolation
Week 4-6
8-port PoE+ recommended - enables VLAN isolation via dual NIC
→ PoE switch ordered
Home Automation Homeowner
Not Started
Install cameras and configure Frigate NVR
Week 20-24
Install after drywall but before paint - coordinate with electrician
→ Frigate running with all cameras
Home Automation Homeowner + Electrician
Not Started
Purchase ZBT-2 Zigbee/Thread adapter if needed for HVAC
Week 4-6
Only needed if HVAC or sensors require Zigbee or Thread
→ Protocol adapter ordered if required
Home Automation Homeowner
Not Started
Configure camera VLAN for network isolation
Week 20-22
Blocks camera internet access while allowing Frigate - security best practice
→ Cameras isolated from main network
Home Automation Homeowner
Not Started
Register for DC SREC program
Week 20-24
Required to sell SRECs
→ SREC registration complete
Energy Homeowner
Not Started
Select SREC aggregator/broker
Week 20-24
SRECTrade or Sol Systems
→ Signed aggregator agreement
Energy Homeowner
Not Started
Verify window closure egress/code compliance
Week 2-4
Verify with DC code: egress, light/ventilation requirements
→ Written confirmation of code compliance for window closure
Engineering Structural Engineer
Not Started
Source high-end furnishings (rugs, couch, table, lamps, chairs)
Week 6-8
Long lead times on custom pieces - order early. Couch 8-16 weeks, rugs 4-8 weeks
→ Furnishing orders placed with lead times tracked
Sourcing Homeowner or Designer
Not Started
Get quotes for window treatments (Living Room and Kitchen drapes)
Week 8-10
Custom window treatments for Living Room ($3k) and Kitchen ($4k)
→ Drape quotes and fabric selections
Sourcing Homeowner or Designer
Not Started
Research humidity control options for 3-floor home
Week 2-3
Steam humidifier + ducted dehumidifier for whole house
→ Equipment recommendations documented
Planning Homeowner or Claude
Not Started
Plan humidity sensor locations per floor
Week 4-6
1 sensor per floor - avoid bathrooms and kitchens
→ Sensor placement plan
Home Automation Homeowner
Not Started
Purchase humidity monitoring sensors
Week 6-8
Aqara or Sonoff Zigbee sensors - requires ZBT-2 adapter
→ Sensors ordered
Procurement Homeowner
Not Started
Verify HVAC system airflow for filtration requirements
Week 4-6
MERV 16 requires adequate static pressure - verify with Manual D
→ Confirmed airflow supports media filter
HVAC HVAC Contractor
Not Started
Select IAQ monitoring system
Week 6-8
Awair Element recommended for Home Assistant integration
→ IAQ monitor selected and ordered
Home Automation Homeowner
Not Started
Plan IAQ sensor locations (one per floor)
Week 6-8
Living areas away from direct HVAC vents - represent breathing zone
→ IAQ sensor placement plan
Home Automation Homeowner
Not Started
Notify neighbors of upcoming work
Week 8-10
Good neighbor relations - especially for rowhouse
→ Neighbors informed
Community Homeowner
Not Started
Plan smart sensor locations - doors windows motion
Week 6-8
Zigbee or Z-Wave sensors based on protocol adapter decision
→ Sensor location plan
Home Automation Homeowner
Not Started
Set up NAS for long-term camera storage
Phase 2
Defer until camera storage needs exceed internal SSD
→ NAS configured for Frigate storage
Home Automation Homeowner
Not Started